Despite an
acknowledged differing site condition by owner, the performance of two EPB TBMs
performed far below predictions and according to purported TBM forces acting on
the rock.
In effect, the penetration rate was
reduced by more than 25% as a consequence of the manufacturer's artificial
limitation of thrust.
Prior to completion of our investigation of the sub-standard
performance on behalf of the contractor, the parties settled

RESOLVED FOR THE BENEFIT OF CONTRACTOR
|