Boulders in Microtunneling
Differing Site Condition
---on behalf of contractor---
Contract
called for prices ($/ft) for 15 feet of tunnel in boulders for a 1000 ft long
tunnel in glacial till.
The contractor used a Soltau Microtunneling machine to excavate the tunnel as
illustrated below.
The contractor encountered unanticipated quantities of boulders, however, how to
identify tunnel sections in boulders?
 A
combination of samples from the separation plant 
and an innovative use of the
microtunneling machine's data logger allowed a demonstration of sections of
tunnel which were in boulders as follows: 
A
comparison of the anticipated (Bill of Quantities) and encountered length of
tunnel in boulders yielded the following results:
With this evidence, the contractor was able to negotiate his costs associated
with the unanticipated length of tunnel in boulders.
CONTRACTOR & OWNER SETTLED
FOR A FAIR COMPENSATION
|