There must be a difference demonstrable between:
reasonable indicated (anticipated) and
well documented encountered conditions;
reasonable anticipated and
well documented encountered construction performance;
There must be a cause-and-effect relationship demonstrable between:
differences in conditions and
differences in construction performance;
There must be a demonstrable impact in time & space on costs;
All contract conditions must be fulfilled:
reliance,
notice, and
mitigation;
No other factors (self inflicted) can have caused the difference between anticipated and encountered performance.
ALL the foregoing elements are required to establish entitlement for a differing site condition claim.
These elements are best prescribed in the contract in association with the differing site condition clause.